Project Updates - March 2

  • Writer: CWB
    CWB
  • 8 hours ago
  • 4 min read

Weekly update from Bobby Tenney (Senior Project Representative) on the Clarksburg Water Board (CWB) and Clarksburg Sanitary Board (CSB) Projects:


This is the update for the week of 2/23 and schedule for the week of 3/2-3/6.


In place of the update photos this week, I’m attaching the information that was mailed out to customers in the areas where the contractors will be working in the next 2-3 months. If you did not receive the informational mailing, that is likely do to the fact that your customer service line is not lead and therefore not being replaced. Please return the Customer Participation Form promptly and keep the other handouts for your records. For the full list of information, click here.


NORTH VIEW AREA – CWB

CONTRACT NO. 1 - BEAR CONTRACTING

The contractor completed installing the new main water line on Hamill Avenue from 19th Street to 20th Street and on 19th Street from Hamill Avenue to Williams Avenue. New customer services on Hamill Avenue between 17th and 18th Streets were installed. Main line tie ins were completed on Hamill Avenue at 18th and 19th Streets. The new main line was started on Williams Avenue between 17th and 19th Street and a new 2” line was installed on 20th Street off West Virginia Avenue.


The schedule for this week is to continue customer services on 19th Street from Hamill Avenue to Williams Avenue. The new main water line installation will continue on Williams Avenue from 19th Street to 20th Street. The new main line installation will also continue on Hamill Avenue from 20th to 21st Street.


NO PARKING signs will be placed in the sections the contractor is planning to work, please find alternate parking during the posted working hours. If your vehicle is parked in the work zone, it will be towed to a safe location if you cannot be located. If you need access to your driveway, please speak to the contractor onsite.


Hamill Avenue will be closed from 20th to 21st Street, 19th Street will be closed from Hamill Avenue to Williams Avenue intersection and Williams Avenue will be closed from 17th Street to 20th Street. Inbound traffic will detour onto 15th Street and outbound traffic will detour to 17th Street; road closed and detour signs will be in place.


Fire and EMS access in North View should not be affected this week.


HARTLAND AND STEALEY AREAS – CWB

CONTRACT NO. 2 - DOSS ENTERPRISES

The contractor completed customer service connections on Temple Terrace, Ryder Avenue, and Rodney Street this past week. The new main waterline was completed in the alley off Euclid Avenue towards Coolidge Street and on Ash Avenue from Coolidge Street to Woodland Avenue. The contractor began laying new main line on Woodland Avenue towards Joseph Street.


The schedule for this week is to complete the new main line on Woodland Avenue from Coolidge Street towards Joseph Street and start on Joseph Street towards Simpson Street.


NO PARKING signs will be placed in the sections the contractor is planning to work, please find alternate parking during the posted work hours. If your vehicle is parked in the work zone, it will be towed to a safe location if you cannot be located. If you need access to your driveway, please speak to the contractor onsite.


Woodland Avenue will be closed from Coolidge Street to Joseph Street except for school buses and residents.


Fire and EMS access to the Stealey area around the park should not be affected. Flaggers are setup in the work area to allow local traffic to enter and exit.


CHESTNUT HILLS (KRAMER DRIVE) – CWB

CONTRACT NO. 3 - D&M CONTRACTING

The contractor has completed the new main water line and services on the project and placed asphalt patch. The final milling and paving are scheduled for next spring when the weather allows.


DOWNTOWN AREA - CWB

CONTRACT NO. 4W - INDEPENDENT ENTERPRISES

The contractor completed the new main water line on 6th Street from West Pike Street to West Main Street and on Chestnut Street to Washington Avenue.

The schedule for this week is to begin laying new main line on Chestnut Street.


between Pike Street and Main Street and in Traders Alley starting at Chestnut Street.

Chestnut Street will be one lane from West Pike Street to West Main Street and Traders Alley will be closed from Chestnut Street to 6th Street this week.


Fire and EMS access should not be affected; traffic will be controlled by flaggers.


DOWNTOWN AREA (WEST END) – CSB

CONTRACT NO. 4S - INDEPENDENT CONTRACTING

The new storm inlets on West Pike Street up to McDonald’s were completed this past week and will continue next week on West Pike Street and West Main Street towards Chestnut Street.


West Main Street will be one lane in the area from McDonalds to Chestnut Street.


Fire and EMS access on the west end of Pike and Main Streets should not be affected, though traffic may be congested at times.