Reporting Period: Week of July 20
Upcoming Schedule: July 27 – July 31
Prepared by: Bobby Tenney, Construction Manager (The Thrasher Group)
NORTH VIEW AREA – CWB
CONTRACT NO. 1 - BEAR CONTRACTING
Work Completed
Completed the new main waterline on Goff Avenue from 23rd Street to 24th Street and installed new customer meter services.
Completed concrete sidewalk repairs on Hamill Avenue and Williams Avenue.
Completed concrete street repairs on Henderson Avenue and Goff Avenue.
Work Scheduled for This Week
Pressure test the new main waterline on Goff Avenue from 20th Street to 24th Street and begin customer service connections.
Complete customer service connections at the end of 18th Street where the new 2-inch mainline was installed.
Continue sidewalk repairs throughout the project.
Traffic Information
NO PARKING signs will be posted in active work areas. Vehicles may be towed if necessary. Please speak with the contractor if driveway access is needed.
Goff Avenue will be closed in sections from 20th Street to 24th Street.
Please follow Road Closed signs and use alternate routes.
Emergency Services: Fire and EMS services in North View are not expected to be affected this week.
HARTLAND AND STEALEY AREAS – CWB
CONTRACT NO. 2 - DOSS ENTERPRISES
Work Completed
Completed new customer service connections on Duff Avenue.
Completed concrete sidewalk repairs on Simpson Avenue, Pick Street, and Duff Avenue.
Continued work on Milford Street from Magnolia Avenue to Hartland Avenue to install the new main waterline and customer services.
Completed paving on Temple Terrace, Euclid Avenue, Coolidge Street, Hall Street, Nicholas Street, Ridenour Street, and Carpenter Street.
Work Scheduled for This Week
Continue concrete repairs throughout the project.
Begin trench paving on Duff Avenue before moving to Milford Street.
Continue work on Milford Street between Magnolia Avenue and Euclid Avenue. Work hours will be 24 hours Monday–Thursday and day shift Friday.
Traffic Information
NO PARKING signs will be posted in active work areas. Vehicles may be towed if necessary. Please speak with the contractor if driveway access is needed.
Milford Street will remain one lane between Magnolia Avenue and Euclid Avenue Monday–Thursday (24 hours) and Friday 7:00 A.M.–7:00 P.M.
Additional streets may be affected as work progresses; daily updates will be posted.
Road Closed signs and flaggers will be in place. Please use alternate routes.
Emergency Services: Fire and EMS services in the Stealey area are not expected to be affected. Flaggers will assist local traffic.
We appreciate your patience and cooperation as we upgrade Clarksburg’s essential water and sewer infrastructure.
For more information or questions, please contact the Construction Manager at (304) 288-8142.