Project Updates - July 14
- CWB

- Jul 14
- 3 min read
CLARKSBURG WATER AND SEWER PROJECT UPDATES
Weekly update from Bobby Tenney (Senior Project Representative) on the Clarksburg Water Board (CWB) and Clarksburg Sanitary Board (CSB) Projects:
This is the update for the week of 7/7– 7/11 and the schedule for the week of 7/14.
As customers are connected to the new water line, informational handouts will be provided to them or left at their residence. These materials will outline the steps residents need to take depending on the material of their existing service line. If a resident's line qualifies for a cost-free replacement, the participation form must be returned to the Thrasher project representative onsite. For any questions regarding the handouts, please speak with the Thrasher representative onsite or contact the CWB, and someone will follow up with you. I am also including the handouts for the customers connected to the new water line.
NORTH VIEW AREA - CWB
CONTRACT NO. 1 - BEAR CONTRACTING
The contractor continued laying the new water line on 14th and 13th Streets this week. The contractor plans to continue with the new line on 14th Street to Franklin Avenue and complete the water line replacement on 13th Street this coming week. The contractor is starting to receive the parts to install the customer services to the new water line and that work will begin this coming week. Once the service connections are completed, the gravel trench will be replaced with an asphalt patch. NO PARKING signs will be placed in the sections the contractor is planning to work, please find alternate parking during working hours. If you need access to your driveway, please speak to the contractor onsite.
Fire and EMS access to 14th Street will be restricted from West Virginia Avenue to Franklin Avenue this coming week.
HARTLAND AND STEALEY AREAS - CWB
CONTRACT NO. 2 - DOSS ENTERPRISES
The contractor continued making customer service connections on Verdun Street, South Alexander and Hartland Avenues. The new main line from Liberty Avenue to Magnolia Avenue, on Reynolds Street, was also started and will be completed this coming week. The schedule for the upcoming week is to continue with customer service connections on Verdun Street, Hartland Avenue and Magnolia Avenue. The contractor will also be continuing with the asphalt trench repairs this coming week. NO PARKING signs will be placed in the areas of the paving work a day ahead of starting on that section. Please find alternate parking during the posted work hours. If your vehicle is parked in the work zone it will be towed to a safe location if you cannot be located. If you need access to your driveway, please speak to the contractor onsite.
Fire and EMS service to the Lower Hartland area should not be affected, though Magnolia Avenue will be closed between Reynolds and Traction Streets. Flaggers are setup in the work area to allow local traffic to enter and exit.
CHESTNUT HILLS (KRAMER DRIVE) - CWB
CONTRACT NO. 3 - D&M CONTRACTING
The contractor has given us a tentative start date of August 4th to start the Chestnut Hills portion of the project.
DOWNTOWN AREA - CWB
CONTRACT NO. 4W - INDEPENDENT ENTERPRISES
The contractor installed a permanent asphalt patch in the trenches along East Pike Street from Oak Avenue to South Park Avenue this past week. The new water line was connected to the existing water line on the side streets along East Pike Street from Linden Avenue to South Park Avenue and those will continue this coming week down to Monticello Avenue. The contractor will also be working night shift this coming week to install the new water line and valves at the intersection of East Main Street and Buckhannon Pike.
Fire and EMS service along East Pike Street should not be affected and one lane of traffic will be controlled by flaggers. The night shift will utilize flaggers at the intersection and Fire and EMS service should not be affected.
DOWNTOWN AREA (WEST END) - CSB
CONTRACT NO. 4S - INDEPENDENT CONTRACTING
The contractor continued the installation of the new sanitary sewer system along with the new storm system at the West Pike/West Main intersection. Due to the location of this work, traffic may not be able to turn from West Pike Street onto West Main Street, flaggers will be onsite to allow traffic to make a U Turn for those wanting to turn onto Main Street. For the upcoming week, work will continue on the new sanitary sewer and storm system from the Pike and Main Streets split and onto West Main Street.
Fire and EMS service in the West End of Pike Street should not be affected, though traffic may be congested at times.