Project Updates - June 9
- CWB

- Jun 9
- 3 min read
Upcoming Schedule: June 8-12
Prepared by: Bobby Tenney, Construction Manager (The Thrasher Group)
NORTH VIEW AREA – CWB
CONTRACT NO. 1 - BEAR CONTRACTING
The contractor is scheduled to begin installation of the new water main along Pride Avenue between 20th Street and 25th Street. Customer service line installations will continue on 19th Street and along Gould Avenue between 19th Street and 25th Street. Customers are reminded to perform a High Velocity Flush after receiving notification that their water service has been transferred to the new mainline.
The paving crew will begin milling and paving operations on Ohio Avenue, West Virginia Avenue, and 13th Street beginning Monday.
NO PARKING signs will be posted in active work zones. Residents are asked to park in alternate locations during posted work hours. Vehicles remaining within designated work zones may be relocated to a safe location if the owner cannot be contacted. Customers requiring driveway access should coordinate directly with the contractor on-site.
Gould Avenue will be closed in sections between 19th Street and 25th Street. Pride Avenue will be closed in sections between 20th Street and 24th Street.
Ohio Avenue, West Virginia Avenue, and 13th Street will experience temporary closures or be reduced to one lane during milling and paving operations.
Road Closed signs and traffic control devices will be in place. Motorists are encouraged to use alternate routes whenever possible.
Fire and EMS services within the North View area are not expected to be affected by this week’s construction activities.
HARTLAND AND STEALEY AREAS – CWB
CONTRACT NO. 2 - DOSS ENTERPRISES
The contractor will continue installation of the new water main on Duff Avenue between Hall Street and Carpenter Street and is scheduled to begin new mainline installation on Morgan Street and Duncan Avenue. Concrete restoration and yard restoration activities will continue throughout the project area.
Customer service line connections will take place on Duff Avenue, Baver Street, and Joseph Street. Customers are reminded to perform a High Velocity Flush after receiving notification that their water service has been transferred to the new mainline.
NO PARKING signs will be posted in active work zones. Residents are asked to utilize alternate parking during posted work hours. Vehicles remaining within designated work zones may be relocated to a safe location if the owner cannot be contacted. Customers requiring driveway access should coordinate directly with the contractor on-site.
Duff Avenue will be closed between Hall Street and Carpenter Street. Morgan Street and Duncan Avenue will experience periodic closures throughout the week as construction progresses.
Road Closed signs, flaggers, and other traffic control measures will be in place. Motorists are encouraged to use alternate routes whenever possible.
Fire and EMS services in the Stealey area, including areas surrounding the park, are not expected to be impacted. Flaggers will be present to assist local traffic entering and exiting the work zone.
CHESTNUT HILLS (KRAMER DRIVE) – CWB
CONTRACT NO. 3 - D&M CONTRACTING
This project is completed.
DOWNTOWN AREA - CWB
CONTRACT NO. 4W - INDEPENDENT ENTERPRISES
The contractor is scheduled to perform milling and paving operations on 3rd Street between Main Street and Pike Street, as well as Traders Alley between Chestnut Street and 4th Street.
Traders Alley and 3rd Street will be closed during milling and paving operations.
Road Closed signs and traffic control measures will be in place. Motorists are encouraged to use alternate routes during construction activities.
DOWNTOWN AREA (WEST END) – CSB
CONTRACT NO. 4S - INDEPENDENT CONTRACTING
This project has been completed.
We appreciate your patience and cooperation as we upgrade Clarksburg’s essential water and sewer infrastructure.
For more information or questions, please contact the Construction Manager at (304) 288-8142.