Project Updates - September 21
Reporting Period: Week of September 21, 2026
Upcoming Schedule: September 28 – October 2, 2026
Prepared by: Bobby Tenney, Construction Manager, The Thrasher Group
NORTH VIEW AREA – CWB
CONTRACT NO. 1 - BEAR CONTRACTING
Work Completed
The contractor continued making customer service connections in the Riverside section and began making trench repairs.
Work Scheduled for This Week
The contractor will complete the remaining customer service connections and asphalt trench repairs in the Riverside section. Concrete sidewalk and curb repairs will also resume throughout the project area.
Traffic Information
NO PARKING signs will be placed in areas where the contractor is scheduled to work. Residents are asked to find alternate parking during the posted working hours. If a vehicle is parked within an active work zone and the owner cannot be located, the vehicle will be moved to a safe location. Residents who need access to their driveways should speak directly with the contractor onsite.
The following streets in the Riverside section may be closed at times during construction activities:
22nd Street
23rd Street
Pearlman Avenue
Green Avenue
Road Closed signs will be in place as necessary. Motorists should use alternate routes and allow additional travel time through the project area.
Emergency Services
Fire and EMS services in North View are not expected to be affected this week.
HARTLAND AND STEALEY AREAS – CWB
CONTRACT NO. 2 - DOSS ENTERPRISES
Work Completed
The contractor completed concrete sidewalk repairs on Milford Street from North Avenue to Park Boulevard. Work continued on Milford Street from North Avenue to Park Boulevard with the installation of new customer service connections. The paving crew also completed street paving on the previously milled streets in Upper Stealey.
A new main waterline was installed on Upper West Woodland Avenue and on Morgan Street from Stealey Avenue to Bond Street.
Work Scheduled for This Week
The contractor will test the new waterline on West Woodland Avenue and complete the mainline installation on Bond Street to Duncan Avenue. Work will continue on Milford Street between North Avenue and Park Boulevard to install new customer service connections and complete concrete sidewalk repairs.
Milling is scheduled to begin on Milford Street from Liberty Avenue to Baker Avenue.
Paving of this section is scheduled to begin on Wednesday, weather and construction conditions permitting.
Traffic Information
NO PARKING signs will be placed in areas where the contractor is scheduled to work. Residents are asked to find alternate parking during the posted working hours. If a vehicle is parked within an active work zone and the owner cannot be located, the vehicle will be moved to a safe location. Residents who need access to their driveways should speak directly with the contractor onsite.
Milford Street will be reduced to one lane in sections from North Avenue to Park Boulevard, Monday through Thursday, from 7:00 A.M. to 7:00 P.M. Milford Street from Liberty Avenue to Baker Avenue will also be affected Monday through Friday, from 7:00 A.M. to 7:00 P.M., for milling and paving operations.
Bond Street will be closed during construction activities. Access to Morgan Street will be available only from Stealey Avenue and McDowell Street.
Additional streets may be affected depending on construction progress. Daily updates will be posted as conditions change.
Road Closed signs and flaggers will be in place as necessary. Motorists should use alternate routes and allow additional travel time through the project area.
Emergency Services
Fire and EMS access to the Stealey area along Milford Street will be affected by construction activities. Flaggers will be stationed within the work area to assist emergency services and allow local traffic to safely enter and exit.
We appreciate your continued patience and cooperation as we upgrade Clarksburg's essential water infrastructure.
For more information or project-related questions, please contact the Construction Manager at (304) 288-8142.