Project Updates - November 3
Reporting Period: Week of October 26, 2026
Upcoming Schedule: November 2 – November 6, 2026
Prepared by: Bobby Tenney, Construction Manager, The Thrasher Group
NORTH VIEW AREA – CWB
CONTRACT NO. 1 - BEAR CONTRACTING
Work Completed
The contractor installed a new main waterline from Franklin Avenue to the entrance of Laurel Lanes. A new valve vault was also installed at the intersection of 12th Street and Richards Avenue to upgrade the existing water system valves and improve the operation of the distribution system.
Work Scheduled for This Week
The contractor will complete testing and disinfection of the newly installed waterlines on 12th Street from Franklin Avenue to Richards Avenue. Once testing and disinfection are completed, crews will begin work on West Virginia Avenue between 21st and 24th Streets to install a new main waterline and customer service connections.
Traffic Information
West Virginia Avenue will be closed to through traffic between 21st Street and 24th Street once waterline construction begins. Motorists should plan to use alternate routes and allow additional travel time through the area.
Road Closed signs and other traffic control measures will be implemented as necessary to maintain safety throughout the construction area.
Emergency Services
Fire and EMS services along West Virginia Avenue are not expected to be affected by the scheduled construction activities.
HARTLAND AND STEALEY AREAS – CWB
CONTRACT NO. 2 - DOSS ENTERPRISES
Work Completed
The contractor continued concrete sidewalk repairs throughout the project area. New main waterlines were installed on Duncan Avenue from Collins Avenue to Winding Way, Lower Bond Street, McDowell Street, and Hart Street. A new main waterline and customer service connections were also installed on Davis Street and Stealey Avenue toward Baker Avenue.
New customer service connections were completed on Bond Street, Hart Street, and Duncan Avenue. Paving was completed on Milford Street from Baker Avenue to the Dollar General Store, including the application of roadway centerline markings.
Additionally, asphalt trench repairs were completed in several areas where new main waterline installations had been finished.
Work Scheduled for This Week
The contractor will begin milling and paving operations on the following streets:
West Woodland Avenue
Joseph Street
Duff Avenue from Joseph Street to Duncan Avenue
King Street
Collins Avenue
Morgan Street
Bond Street
Stealey Avenue
Main waterline and customer service installations will continue on Duff Avenue, Baker Avenue, Stealey Avenue, and Hart Street. Concrete crews will also continue sidewalk repairs throughout the project area.
Scheduled Water Service Interruptions
Water service interruptions are scheduled for Monday through Thursday, November 2–5, 2026, between 8:00 A.M. and 5:00 P.M. The affected areas include customers on and off Duncan Avenue from Duff Avenue to Bond Street and from Morgan Street to Hart Street.
These interruptions are necessary to allow construction crews to connect newly installed main waterlines to the existing water distribution system. Water service is not expected to be interrupted for the entire day; however, interruptions may occur at any time during the posted hours as the tie-in work progresses.
Construction delays, unforeseen conditions, or inclement weather may cause water service interruptions to extend beyond the anticipated restoration times. Crews will work to restore service as quickly and safely as possible.
Traffic Information
NO PARKING signs will be placed in areas where the contractor is scheduled to work. Residents are asked to find alternate parking during the posted working hours. If a vehicle is parked within an active work zone and the owner cannot be located, the vehicle will be moved to a safe location. Residents who need access to their driveways should speak directly with the contractor onsite.
The following streets may be reduced to one lane or temporarily closed during construction activities:
Hart Street
McDowell Street
Bond Street
West Woodland Avenue
Duncan Avenue
Joseph Street
Collins Avenue
Davis Street
Stealey Avenue
Duff Avenue
Baker Avenue
Additional streets may be affected depending on construction progress. Daily updates will be posted as conditions change.
Road Closed signs and flaggers will be in place as necessary. Motorists are encouraged to use alternate routes, exercise caution when traveling through construction zones, and allow additional travel time.
Emergency Services
Fire and EMS access throughout the Stealey area will be affected by construction activities. Flaggers will be stationed within active work zones to assist emergency vehicles and allow local traffic to safely enter and exit. Traffic control measures will be implemented to maintain access for emergency responders whenever possible.
We appreciate your continued patience, understanding, and cooperation as we make these important improvements to Clarksburg's water distribution system. These investments are essential to improving water service reliability, strengthening infrastructure, and ensuring a safe and dependable water supply for our customers and community.