Project Updates - September 14
Reporting Period: Week of September 14, 2026
Upcoming Schedule: September 21 – September 25, 2026
Prepared by: Bobby Tenney, Construction Manager, The Thrasher Group
NORTH VIEW AREA – CWB
CONTRACT NO. 1 - BEAR CONTRACTING
Work Completed
The contractor completed installation of the new main waterline in the Riverside area and began replacing customer service connections.
Work Scheduled for This Week
The contractor will continue replacing customer service connections and begin yard and concrete restoration throughout the Riverside area.
Traffic Information
NO PARKING signs will be placed in areas where the contractor is scheduled to work. Residents are asked to find alternate parking during the posted working hours. If a vehicle is parked within an active work zone and the owner cannot be located, the vehicle will be moved to a safe location. Residents who need access to their driveways should speak directly with the contractor onsite.
The following streets may be closed at times during construction activities:
21st Street
22nd Street
23rd Street
Pearlman Avenue
Henderson Avenue from 20th Street to 21st Street
Road Closed signs will be in place as necessary. Motorists should use alternate routes and allow additional travel time through the project area.
Emergency Services
Fire and EMS services in North View are not expected to be affected this week.
HARTLAND AND STEALEY AREAS – CWB
CONTRACT NO. 2 - DOSS ENTERPRISES
Work Completed
The contractor completed concrete sidewalk repairs on Milford Street from Hall Street to North Avenue. Work continued on Milford Street from North Avenue to Park Boulevard with the installation of new customer service connections. The paving crew completed street milling on several streets and began paving those streets on Thursday.
A new main waterline was installed on Upper West Woodland Avenue and on Morgan Street from Stealey Avenue to Bond Street.
Work Scheduled for This Week
The contractor will complete and test the new waterline on West Woodland Avenue. Crews will also complete the mainline installation on Morgan Street and begin installing the new mainline along Bond Street toward Duncan Avenue.
Work will continue on Milford Street between North Avenue and Park Boulevard to install new customer service connections and complete concrete sidewalk repairs. Paving is scheduled to continue on Joseph Street, Duff Avenue, Ash Avenue, Hall Street, and Ryder Avenue, weather permitting.
A scheduled water service interruption will occur on Monday, September 21, 2026, from 8:00 A.M. to 5:00 P.M. If the work cannot be completed as scheduled, the make-up date will be Tuesday, September 22, 2026, during the same hours. Customers in the area between Baker Avenue and Park Boulevard on both sides of Milford Street will be affected. The Clarksburg Water Board will contact customers who are expected to experience an interruption in water service.
Traffic Information
NO PARKING signs will be placed in areas where the contractor is scheduled to work. Residents are asked to find alternate parking during the posted working hours. If a vehicle is parked within an active work zone and the owner cannot be located, the vehicle will be moved to a safe location. Residents who need access to their driveways should speak directly with the contractor onsite.
Milford Street will be reduced to one lane in sections from North Avenue to Park Boulevard, Monday through Friday, from 7:00 A.M. to 7:00 P.M.
Bond Street will be closed during construction activities. Access to Morgan Street will be available only from Stealey Avenue and McDowell Street.
Additional streets may be affected depending on construction progress. Daily updates will be posted as conditions change.
Road Closed signs and flaggers will be in place as necessary. Motorists should use alternate routes and allow additional travel time through the project area.
Emergency Services
Fire and EMS access to the Stealey area along Milford Street will be affected by construction activities. Flaggers will be stationed within the work area to assist emergency services and allow local traffic to safely enter and exit.
We appreciate your continued patience and cooperation as we upgrade Clarksburg's essential water infrastructure.
For more information or project-related questions, please contact the Construction Manager at (304) 288-8142.




