Weekly update from Bobby Tenney (Senior Project Representative) on the Clarksburg Water Board (CWB) and Clarksburg Sanitary Board (CSB) Projects:

This is the update for the week of 5/26 – 5/30 and the schedule for the week of 6/2.


NORTH VIEW AREA - CWB

CONTRACT NO. 1 - BEAR CONTRACTING

The contractor finished installing and testing the new water line on North Ohio Avenue to the entrance of the Harrison County Emergency Squad and started laying the new water line on WV Avenue. The contractor also started placing concrete in the trench on Ohio Avenue and will continue and complete that work next week. Work will continue on the new water line on WV Ave towards 15th street this coming week. Traffic will be restricted to one lane during this phase of the work, and flaggers will be in place to control traffic.

Access to the Clarksburg Fire Department, Harrison County Emergency Squad, North Ohio Ave, 12th, 13th, and 14th Streets will be maintained and controlled by the flaggers onsite.


HARTLAND/STEALEY AREA - CWB

CONTRACT NO. 2 - DOSS ENTERPRISES

The contractor has tested and disinfected the new water line that was previously installed on Hartland Avenue, South Alexander, and Verdun Street from the corner of Hartland Avenue. The work on Verdun Street was completed this week, and the contractor started on Magnolia Avenue. The work schedule for the upcoming week is to continue installing the new 6” water line on Magnolia Avenue and install customer services on Riverside Drive and Bridge Street.

Fire and EMS service to the Verdun Street area should not be affected. Flaggers are set up in the work area to allow local traffic to enter and exit.


ARMORY ROAD - CWB

CONTRACT NO. 3 - D&M CONTRACTING

The contractor has moved on to another project until the materials for the Chestnut Hills portion of the project arrive. It is anticipated that the materials will arrive sometime in late August to early September.


DOWNTOWN AREA - CWB

CONTRACT NO. 4W - INDEPENDENT ENTERPRISES

The contractor continued installing the new customer service connections along East Pike Street and placing the permanent trench repairs. The work schedule for next week will be to continue with customer service connections along East Pike Street from Linden Avenue towards Monticello Avenue and start installing the new main water line on Main Street from EB Saunders Way towards 2nd Street.

Fire and EMS service to the streets off East Pike Street could be affected this coming week. The work on Main Street will only affect one lane, and no disruptions should occur. Flaggers will be on site to help with rerouting service.


DOWNTOWN AREA (NEAR WENDY'S) - CSB

CONTRACT NO. 4S - INDEPENDENT CONTRACTING

The contractor continued the installation of the new sanitary sewer system along with the new storm system from O’Reilly Auto Parts towards McDonald's this week. For the upcoming week, work will continue on the new sanitary sewer and storm system along West Pike Street in that same area.

Fire and EMS service in the West End of Pike Street should not be affected, though traffic may be congested at times.

 