This is a full progress update covering all work completed from the beginning of construction to today (3/13/2026).
North View Area: 40% Complete
Waterline - 21,178 feet of 36,000 feet installed
Services - 427 services completed of 890 services, 285 being lead
Fire Hydrants – 37 out of 70 installed
Heartland and Stealey Areas: 23% Complete
Waterline – 17,578 feet of 53,600 feet installed
Services – 233 services completed of 1,448 services, 110 being lead
Fire Hydrants – 33 out of 105 installed
Chestnut Hills (Kramer Drive) Area: 98% Complete
Waterline – 6,589 feet of 6,589 feet installed
Paving remaining
Main and Pike Street Area: 75% Complete
Waterline – 18,713 feet of 20,895 feet installed
Services – 159 services completed of 232 services, 93 being lead
Fire Hydrants – 38 out of 41 installed