Project Updates

  • Writer: CWB
    CWB
  • Mar 13
  • 1 min read

Updated: Mar 16

This is a full progress update covering all work completed from the beginning of construction to today (3/13/2026).


North View Area: 40% Complete

  • Waterline - 21,178 feet of 36,000 feet installed

  • Services - 427 services completed of 890 services, 285 being lead

  • Fire Hydrants – 37 out of 70 installed


Heartland and Stealey Areas: 23% Complete

  • Waterline – 17,578 feet of 53,600 feet installed

  • Services – 233 services completed of 1,448 services, 110 being lead

  • Fire Hydrants – 33 out of 105 installed


Chestnut Hills (Kramer Drive) Area: 98% Complete

  • Waterline – 6,589 feet of 6,589 feet installed

  • Paving remaining


Main and Pike Street Area: 75% Complete

  • Waterline – 18,713 feet of 20,895 feet installed

  • Services – 159 services completed of 232 services, 93 being lead

  • Fire Hydrants – 38 out of 41 installed


If you have any questions, please call our Customer Service Center at (304) 623-3711.